Construction Oversight on Complex Residential Projects

How accountability structures determine whether your project stays on budget - and why the contract you choose matters more than the people you hire to watch it.

The question isn't "do I need someone watching my contractor." The question is why your contract structure requires watching in the first place - and whether a different structure eliminates the need.

Last updated: February 2026

About This Page
This page is written by Jeff Benson, Principal of Benson Construction Group, drawing on 24 years of experience managing complex residential projects under multiple delivery models - including lump-sum, cost-plus, CM advisory, and CM at Risk structures. The analysis reflects how these models function in practice on $3M-$20M+ residential projects in Los Angeles, not how they're described in textbooks. The goal is to give you the structural framework to evaluate your options - regardless of whether you work with us.

1. The Question Nobody Asks Correctly

Every owner building a $5M+ custom home in Los Angeles hears the same advice. Their real estate attorney says it. Their business manager says it. Their architect's office manager says it. Sometimes even their architect says it, though usually with less conviction: Make sure you have someone watching the contractor.

This advice is well-intentioned. Depending on the contract structure the owner has chosen, it might even be correct. But it skips a more fundamental question that almost nobody thinks to ask: why does the contractor need watching in the first place?

The instinctive answer is that contractors are untrustworthy. Some are. But that's not the structural explanation. The structural explanation is that most construction contracts create conditions where the contractor's financial interests and the owner's financial interests pull in opposite directions. When a contractor makes more money by spending more of your money - or by interpreting ambiguity in their favor rather than yours - the relationship becomes adversarial not because anyone is acting in bad faith, but because the contract rewards it.

When interests diverge, oversight becomes necessary. That's the logic behind the owner's representative role: hire an independent professional who understands construction, who can review costs, monitor quality, evaluate change orders, and represent your interests against the contractor's interests. It's a rational solution to a real problem.

But it's a compensating control, not a fix. You're adding a layer of management on top of a structure that creates the conflict. You're paying two parties - a builder whose contract doesn't align their incentives with yours, and a watchdog whose job is to compensate for that misalignment. Two management layers, two fee structures, and an adversarial dynamic baked into the project from day one.

The better question - the one this page exists to answer - is: what if you chose a contract structure that aligned the builder's financial interests with yours from the start? If the builder absorbs cost overruns, benefits from cost savings, and operates with full cost transparency, does the owner still need a third party watching?

That's the reframe. The question isn't "do I need an owner's rep?" The question is: "What contract structure am I using, and does that structure align the builder's incentives with mine?" If it does, the oversight question answers itself. If it doesn't, then yes, you need someone watching - but you should also ask why you chose a structure that requires it.

The Three Structural Elements That Determine Every Project's Outcome

Every construction contract - regardless of how it's labeled or who sells it - answers three questions. The answers determine the dynamic of the project, the relationships between the parties, and ultimately whether the owner's investment is protected or exposed.

Who carries the cost risk? When the project costs more than expected - and on complex residential projects, something always costs more than expected - who absorbs the overage? Does it come out of the contractor's margin, or does the owner write another check? The answer determines whether the contractor is incentivized to manage costs or pass them through.

Who benefits from cost savings? When the project team finds a more efficient approach - a structural solution that saves $80,000, a material substitution that achieves the same performance at lower cost - who captures that savings? If the contractor keeps it, the owner funded the inefficiency in the original estimate. If the owner keeps it, the contractor has no incentive to find efficiencies. If they share it, both parties are pulling in the same direction.

Who controls the cost information? Who sees the actual numbers? Does the owner see the subcontractor bids, the material invoices, the labor costs? Or does the owner see a lump-sum number with the details locked inside the contractor's accounting system? Cost visibility determines whether the owner can evaluate their project's financial health or must rely on someone else's summary.

These three elements - risk allocation, savings incentive, and information transparency - are the structural DNA of every construction contract. They determine more about how your project will play out than the personality of your contractor, the reputation of your architect, or the experience of your project manager. Good people operating within a misaligned structure will still produce adversarial outcomes. Aligned people operating within an aligned structure will produce collaborative ones.

There's a fourth element that most analyses miss: who already has oversight obligations. Under the standard AIA agreement used on the vast majority of custom residential projects, the architect has contractual responsibilities for construction administration - site visits, pay application review, change order evaluation, submittal review. The owner is already paying a licensed professional to observe the work and protect their interests. Understanding this reframes the entire oversight question, because it means the choice isn't between "oversight" and "no oversight." It's between duplicating the architect's oversight with an additional layer, or supporting the architect's oversight with a construction partner whose incentives are already aligned. For a detailed treatment of the architect's responsibilities and how they interact with other project roles, see our guide on the architect's role in the CMAR model.

The rest of this page walks through each contract structure, shows you the math, explains the risk allocation, and gives you a framework to evaluate which model fits your project. Not because one model is always right - it isn't - but because understanding the structure lets you make the decision from a position of knowledge rather than relying on whoever's advice you heard last.

2. How Construction Contracts Create Incentive Structures

This section is the educational core. It explains how each major contract type functions in practice on complex residential projects - not in a textbook, not on a commercial office building, but on a $5M-$15M custom home in Los Angeles where design evolves, site conditions create surprises, and the owner is personally invested in every finish selection.

Every contract type described here is legitimate. Each one works under the right conditions. The question is whether the conditions of your project match the assumptions built into the contract - and what happens when they don't.

Lump-Sum (Fixed Price) Contracts

How it works in theory: The contractor reviews the construction documents, prices every element of the work, adds their overhead and profit, and submits a fixed price. The owner accepts the price. If the project costs less to build than the contractor estimated, the contractor keeps the difference as additional profit. If the project costs more, the contractor absorbs the overage. The owner pays a fixed number and the contractor manages the risk.

How it works in practice on luxury residential: The fixed-price model works beautifully when the scope is fully defined, the documents are complete and unambiguous, the site conditions are known, and the owner makes no changes. On a kitchen remodel with finished architectural drawings and a locked specification, lump-sum is clean and efficient.

On a $7M hillside home with complex foundation systems, evolving design, owner selections that won't be finalized for months, and site conditions that won't be fully understood until excavation - the "defined scope" that the fixed price depends on doesn't exist at bid time. Construction documents on custom residential projects contain ambiguities. Not because the architect is careless, but because custom design involves thousands of decisions that are still being refined when the documents go to bid.

Every ambiguity becomes a change order negotiation. The contractor's financial incentive is to interpret scope narrowly: anything not explicitly shown or dimensioned on the drawings is "extra." The owner's financial incentive is to interpret scope broadly: "I assumed the drawings implied that was included." Neither party is being dishonest. They're each responding rationally to the incentive structure the contract created.

The dynamic becomes adversarial from the first change order. The contractor bid the project tight to win the work - because on a competitive lump-sum bid, the lowest number usually wins. They need change order margin to make the job profitable. That's not a character flaw; it's a business reality. The owner feels nickeled-and-dimed by every change order. The contractor feels the owner is trying to extract free work. The structure created the conflict.

There's a subtler problem: the lump-sum contractor has no incentive to show you their costs. You don't see what they're paying subcontractors, what their material costs are, or where their margin sits. The fixed price is a black box. If the contractor finds a way to build the structure for $200,000 less than they estimated, that savings belongs to them. You funded the estimate; they captured the efficiency. You'll never know it happened.

Where lump-sum works well: Simple projects with well-defined scope, minimal anticipated changes, straightforward site conditions, and a completed set of construction documents. A spec home where every detail is already decided. A tenant improvement with a fixed floor plan and standard finishes. Not a custom residence where the owner is selecting stone in month eight of a fourteen-month build.

Cost-Plus (Time and Materials) Contracts

How it works in theory: The contractor bills the owner for all actual costs - labor, materials, subcontractors, equipment, permits - plus a markup that represents the contractor's overhead and profit. The markup is typically expressed as a percentage of cost (15-25% on residential projects in Los Angeles) or occasionally as a fixed fee. The owner pays the real cost of the work plus the contractor's compensation. There's no fixed price. The owner pays what it costs.

How it works in practice on luxury residential: Cost-plus is the most common contract structure on high-end residential projects in Los Angeles, and it's easy to understand why. Custom homes involve evolving design, extensive owner selections, and the kind of complexity that makes lump-sum bidding impractical. Cost-plus accommodates change naturally - every modification is simply billed at cost plus the markup.

The structural problem is the incentive alignment. When the contractor's fee is a percentage of cost, more cost means more fee. A $100,000 problem solved with $30,000 of smart engineering generates $4,500-$7,500 in contractor fee (at 15-25% markup). The same problem addressed with $100,000 of additional construction generates $15,000-$25,000 in fee. The contract doesn't reward efficiency. It rewards spending.

This doesn't mean every cost-plus contractor inflates costs. Many are ethical professionals who manage costs diligently because their reputation depends on it. But the structure doesn't require cost discipline, and it doesn't reward it. On a $10M project over 18 months, with thousands of individual cost decisions, the cumulative effect of a structure that doesn't incentivize efficiency is significant - even when nobody is acting in bad faith.

The transparency problem. Cost-plus is often marketed as "transparent" because the owner sees invoices. In practice, the owner sees a monthly stack of subcontractor invoices, material receipts, and labor reports that they have no independent basis to evaluate. Was the framing subcontractor's price competitive, or did the GC use a preferred sub who charges a premium? Is the concrete unit price in line with current market rates? Are the general conditions costs - site supervision, temporary power, equipment rental, dumpsters, portable facilities - appropriate for this project's scope and schedule, or are they running higher than they should?

Without construction knowledge, invoice visibility is not cost transparency. It's data without context. You can see every number without understanding whether any of them are right.

This is exactly where the owner's rep enters. Someone needs to review those invoices with the expertise to evaluate them. Someone needs to compare the subcontractor pricing to market rates, monitor the general conditions burn rate, question whether the project is staffed appropriately, and report to the owner on whether the costs are reasonable. The owner's rep fills this role, and it's a genuinely valuable service when the underlying contract structure is cost-plus.

But consider what the owner is now paying: a contractor markup of 15-25% on every dollar of cost, plus an owner's rep fee of 3-5% of construction cost to monitor those costs. On an $8M project, that's $1.2M-$2.0M in contractor markup plus $240,000-$400,000 in owner's rep fees. The combined management cost is $1.4M-$2.4M - with no cost guarantee, no cost ceiling, and no contractual mechanism that rewards anyone for bringing the project in under budget.

The owner is paying 18-30% in combined management costs on a structure that provides no budget certainty. That's not an argument against the people involved. It's an observation about the structure.

Guaranteed Maximum Price (GMP) / CM at Risk

How it works: The construction manager provides a Guaranteed Maximum Price - a cost ceiling that includes all construction costs (subcontractors, materials, labor, equipment), the CM's fee (fixed, not a percentage of cost), and a defined contingency for unforeseen conditions. If the project costs more than the GMP, the CM absorbs the overage from their own margin. If the project costs less, the savings are shared between the owner and the CM according to a pre-agreed split - typically 75/25 or 70/30, with the majority going to the owner.

All costs pass through at actual cost with open-book accounting. The owner sees every subcontractor bid, every invoice, every material receipt, every contingency draw. For a complete explanation of the CMAR model and how it works, see our foundational guide.

How it works in practice on luxury residential: The GMP fundamentally changes the three structural elements.

Who carries cost risk? The CM. Overruns come out of their pocket. This means the CM is financially motivated to manage costs, catch problems early, and solve issues efficiently - not because they're better people than a cost-plus GC, but because the contract makes cost management a matter of self-interest.

Who benefits from savings? Both parties. The shared savings mechanism means the CM is incentivized to find efficiencies - a less expensive structural approach that achieves the same engineering performance, a subcontractor who can deliver the same quality at a better price, a scheduling sequence that reduces general conditions duration. Every dollar saved generates $0.25-$0.30 for the CM. That's real money on a $10M project where attentive management might save $300,000-$500,000. The owner captures the majority of those savings.

Who sees the numbers? Everyone. Open-book accounting means the owner has full visibility into costs - not invoice visibility after the fact, but competitive bid visibility before subcontracts are awarded, real-time cost tracking during construction, and a complete reconciliation at project close.

How the GMP is set. This is critical, because it distinguishes the GMP from a lump-sum bid. A lump-sum bid is produced in a vacuum - the contractor looks at drawings, makes assumptions about what they mean, and submits a number. The GMP is the product of a pre-construction process where the CM has been involved during design, providing real-time cost feedback as decisions are made, reviewing every drawing for constructability and cost implications, and developing detailed pricing with competitive subcontractor bids.

By the time the GMP is established - typically at the completion of construction documents - the owner has been tracking the budget evolution from feasibility through schematic design, design development, and construction documents. The CM has priced every trade package with input from qualified subcontractors. The architect has participated in this process as a full design partner, with their design authority respected while the CM provides cost and constructability data. There are no bid-day surprises because the budget has been developed collaboratively over months, not estimated in isolation.

The adversarial dynamic doesn't develop because both parties benefit from the same outcome: completing the project at or under the GMP. The contractor isn't trying to maximize change orders because change orders that increase the GMP don't increase their fee - and changes that don't warrant a GMP amendment come out of their contingency. The owner isn't fighting over scope interpretation because the pre-construction process resolved ambiguities before the GMP was set, and the open-book accounting means they can see exactly what every element of the work costs.

The Structural Question
On every project, ask three questions: Who absorbs cost overruns? Who benefits from cost savings? Who sees the actual numbers? The answers define whether your contract structure creates alignment or requires oversight. A fourth question most people miss: Who already has oversight obligations? Your architect, under the standard AIA agreement, is already contractually responsible for construction administration. That changes the calculus on whether you need additional oversight - or a structure that supports the oversight you're already paying for.

3. The Real Cost of Construction Oversight - Show the Math

This is the section nobody else publishes. Owner's rep companies don't want their fee structure displayed next to an alternative that eliminates the need for their services. General contractors on cost-plus contracts don't want the cumulative management cost made explicit. And most content about construction delivery methods stays at the conceptual level - "fees vary" and "every project is different" - without showing the reader what the numbers actually look like.

Every project is different. But the structural math is consistent enough to model. Here's what the numbers look like on a representative $8M residential project in Los Angeles - the kind of complex hillside home or significant renovation where this decision matters most.

Scenario A: Cost-Plus General Contractor + Owner's Representative

  • Construction cost (labor, materials, subcontractors, equipment): $8,000,000
  • GC markup (20% on cost-plus - mid-range for LA luxury residential): $1,600,000
  • Owner's rep fee (4% of construction cost): $320,000
  • Total management cost to the owner: $1,920,000 (24% of construction cost)
  • Cost guarantee: None. The GC has no contractual obligation to deliver the project at any specific cost.
  • Cost overrun responsibility: Owner. If the project runs over the estimate, the owner pays the additional cost - plus 20% markup on every dollar of overage.
  • Budget certainty: Low. The cost-plus estimate is a projection, not a commitment. On a complex project, actual costs can vary 10-25% from the initial estimate.
  • If costs rise 10%: The owner pays an additional $800,000 in construction cost, plus $160,000 in additional GC markup, plus approximately $32,000 in additional owner's rep fees. Total additional exposure: $992,000.

Scenario B: Lump-Sum General Contractor + Owner's Representative

  • GC lump-sum bid: $9,200,000 (includes a risk premium because the GC is pricing scope ambiguity, design uncertainty, and cost escalation into the fixed number)
  • Owner's rep fee (4% of the bid amount): $368,000
  • Total visible cost: $9,568,000
  • Cost guarantee: For the base scope only. Everything outside the lump-sum scope is processed as a change order at the GC's pricing, typically with a 20-30% markup on change order work.
  • Cost overrun responsibility: GC for base scope (in theory). Owner for everything else. On a custom residential project, "everything else" is substantial - change orders commonly add 10-20% to the original contract.
  • If the owner makes $800,000 in changes: The owner pays $800,000 plus 20-30% GC markup on changes ($160,000-$240,000), plus additional owner's rep fees. The lump-sum "guarantee" doesn't apply to anything outside the original scope.

Scenario C: CMAR (Guaranteed Maximum Price)

  • Construction cost at actual (open-book, competitively bid subcontractor packages): $7,600,000
  • CM fee (fixed, negotiated during pre-construction): $570,000 (7.5% of construction cost)
  • Construction contingency (within the GMP): Included in the GMP
  • GMP: $8,170,000 (construction cost + CM fee + contingency)
  • Total management cost to the owner: $570,000 (7.5% of construction cost)
  • Cost guarantee: Yes. The GMP is a contractual ceiling. If the project costs more, the CM absorbs the overage.
  • If the project comes in at $7,400,000: The underage is $770,000. The owner receives 75% ($577,500). The CM receives 25% ($192,500). Both parties benefit.
  • If costs rise 10% due to CM's estimating: The CM absorbs the overage. The owner's cost does not change.

The Comparison Table

Element Cost-Plus GC + Owner's Rep Lump-Sum GC + Owner's Rep CMAR (GMP)
Total management cost $1,920,000 (24%) Embedded in bid + $368,000 $570,000 (7.5%)
Cost guarantee No Base scope only Yes - full GMP
Overrun responsibility Owner Owner (for changes) CM
Cost visibility Invoice review after the fact None (black box) Full open-book, real-time
Incentive alignment GC earns more when costs rise GC profits from ambiguity CM benefits from efficiency
Savings sharing No mechanism No mechanism 75/25 owner/CM
If costs rise 10% Owner pays ~$992,000 more Owner pays change order markup CM absorbs overage
If costs come in 5% under GC keeps savings (invisible) GC keeps savings (in bid) Owner receives 75% of savings

What the $1.35M Difference Buys

The difference between Scenario A ($1,920,000 in management costs) and Scenario C ($570,000 in management costs) is approximately $1,350,000. That's not a rounding error. On an $8M project, $1.35M is the price of the kitchen, or the entire landscape package, or a meaningful reduction in the project's debt service.

$1.35M
Management Cost Difference
Between Cost-Plus + Rep vs. CMAR
24% vs 7.5%
Total Management Cost
as % of Construction
$0
Owner's Cost Increase
if CMAR Overruns GMP

That $1.35M doesn't buy a better house. It doesn't buy better materials, better craftsmanship, or a better design. It buys a structural gap - the cost of having an incentive structure that requires filling with additional oversight - that a different contract structure would have eliminated.

The reader can adjust these numbers for their own project. The percentages are representative of Los Angeles luxury residential market rates. The structural relationships hold across project sizes. For a broader analysis of what drives construction costs in Los Angeles, including per-square-foot ranges by project type and complexity, see our cost guide.

Where the Money Goes
On an $8M project with a cost-plus contractor and an owner's rep, the owner is paying $1.9M+ in combined management costs with no cost ceiling. Under a GMP structure, the owner is paying $570K in management cost with a contractual cost ceiling and shared savings. The difference - $1.35M+ - doesn't build a better house. It fills a structural gap that a different contract would have eliminated.

4. Why the Owner's Rep Role Exists - Honest Assessment

If the structural argument in the previous sections is going to be credible, it has to start with an honest assessment of the role it reframes. The owner's representative exists because of a real problem, and on many projects, the role provides genuine value. Understanding when and why is essential to understanding when the role is necessary and when a different structure makes it redundant.

The Problem the Owner's Rep Solves

Traditional construction contracts - lump-sum and cost-plus - create conditions where the contractor's financial interests can diverge from the owner's. On complex projects involving millions of dollars and 12-24 months of construction, an owner who doesn't have construction knowledge is operating at an enormous information disadvantage.

The contractor speaks a technical language the owner doesn't share. Subcontractor bids contain line items the owner can't evaluate. Change order pricing includes markups the owner can't benchmark. Schedule decisions have cost implications the owner can't see. Quality judgments require construction experience the owner doesn't have.

The owner's rep bridges this gap. They're an independent construction professional - typically someone with project management or construction management background - who represents the owner's interests. They speak the contractor's language. They can evaluate pricing independently. They can identify quality issues before they become expensive. They can tell the owner whether a change order is reasonable, whether the schedule is realistic, whether the subcontractor work meets the specification.

What a Good Owner's Rep Actually Does

On a project where their role is well-defined and the contract structure warrants their involvement, a competent owner's rep provides real services:

  • Reviews subcontractor bids and evaluates whether pricing is competitive for the scope and current market conditions
  • Monitors construction progress through regular site visits and compares actual progress to the published schedule
  • Reviews change orders, evaluates the scope validity, and assesses whether the pricing is reasonable
  • Tracks the owner's budget and reports expenditures against the approved budget
  • Coordinates communication between the owner, architect, and contractor - particularly when the owner doesn't have the bandwidth or technical knowledge to process construction information directly
  • Provides regular written reporting on project status, budget position, and risk items

For an owner who has already engaged a general contractor under a lump-sum or cost-plus contract, this service provides essential protection. The information asymmetry between a $10M contractor with decades of experience and a homeowner - even a highly sophisticated one who runs a hedge fund or manages a private equity portfolio - is enormous in the construction domain. Having someone on the owner's side of the table who understands the contractor's world is genuinely valuable when the contract structure creates opposing interests.

The Structural Observation

Here's where the analysis shifts - not from appreciation to attack, but from describing the role to describing its structural position.

The owner's rep is a compensating control. They don't change the incentive structure; they add oversight to a structure that requires it. The contractor's financial interests still diverge from the owner's. The change order dynamic still exists. The cost information still originates with the contractor. The owner's rep monitors, evaluates, and advises - but the underlying structure that creates the need for monitoring hasn't changed.

The question for the owner isn't whether the owner's rep is good at their job. It's whether to accept a contract structure that requires a watchdog, or to choose a structure that doesn't require one. Both are legitimate choices. But they should be conscious choices made with full understanding of the structural implications - not reflexive decisions made because "everyone says you need an owner's rep."

When an Owner's Rep IS the Right Answer

There are project conditions where the owner's rep role is appropriate, valuable, and worth the fee:

When a GC is already under contract. If you've already signed a lump-sum or cost-plus contract with a general contractor, the incentive structure is set. You need oversight within that structure, and a good owner's rep provides it. Restructuring the delivery model mid-project isn't realistic.

When the project is relatively straightforward. On projects under $2M with standard site conditions, a trusted contractor, and well-defined scope, advisory oversight may be sufficient. The complexity doesn't justify a full CMAR engagement with pre-construction services and GMP development.

When the owner wants advisory support without CM holding subcontracts. Some owners prefer to maintain direct contracts with a general contractor and have a consultant providing independent oversight. This is a matter of preference and control, and it's a legitimate choice.

When the owner is managing an architect selection or design competition. Before a delivery model is selected, an experienced advisor can help the owner navigate the process of selecting design and construction teams.

Where the Owner's Rep Creates Unintended Friction

These are structural observations about scope overlap, not criticisms of professional competence. On projects where both an owner's rep and an architect are engaged - which is nearly every custom residential project - certain friction points emerge consistently:

Communication layering. The owner's rep adds a management layer between the owner and the project team. Decisions that previously flowed directly between the architect, contractor, and owner now route through an intermediary. On time-sensitive construction decisions, the additional layer can slow the process from hours to days.

Budget opinions vs. construction-informed cost data. Most owner's reps come from project management or real estate backgrounds. They may not have the estimating infrastructure - trade databases, subcontractor relationships, quantity takeoff capability - to produce independent cost analysis. Their budget input tends to be evaluative ("that seems high") rather than constructive ("here's what that scope should cost based on competitive market data").

Overlap with the architect's construction administration role. This is the friction point with the most significant project impact, and it's worth its own section. The architect is already contractually obligated under the AIA B101 to review pay applications, evaluate change orders, and observe construction. The owner's rep often duplicates these functions, creating two overlapping oversight structures without clear hierarchy. For a detailed discussion of the architect's construction administration responsibilities and how they interact with other project roles, see our guide on the architect's role.

Dilution of the architect's direct relationship with the owner. The architect designed the building. They understand every detail of the drawings, every design decision, every trade-off between cost and design intent. When an intermediary reviews the architect's recommendations before they reach the owner - adding commentary, reframing design decisions in management language, filtering professional judgment through a non-design lens - the owner receives a managed version of their architect's expertise instead of the expertise itself.

Dual fee structures without dual guarantees. The owner pays the contractor's markup for construction execution and the owner's rep's fee for oversight - but neither party provides a cost guarantee. The advisory model generates fees for two management layers while the cost risk remains entirely with the owner.

5. The Architect as the Owner's Natural Oversight - And What Happens When That Role Is Undermined

This section makes an argument that nobody else in the industry articulates online, and it's the argument that changes the oversight conversation entirely: the owner already has a trusted professional with construction oversight obligations - their architect. The owner's rep role doesn't just add a layer of management; in practice, it often duplicates and dilutes the architect's contractual authority in ways that harm the project.

What the Architect Is Already Contractually Obligated to Do

The AIA B101 - the Standard Form of Agreement Between Owner and Architect - is the contract used on the vast majority of custom residential projects in Los Angeles. Under the B101, the architect's scope of services includes Construction Administration (CA), and CA is not a courtesy service or an optional add-on. It's a contractual obligation that the architect has agreed to perform as part of their professional fee.

Under their CA obligations, the architect is contractually required to:

Visit the site at intervals appropriate to the stage of construction to evaluate whether the work is proceeding in general accordance with the contract documents. These aren't casual walk-throughs. The architect is the professional who designed the building, who understands every detail of the drawings, and who can identify when the work deviates from the design intent.

Review and certify the contractor's applications for payment. This is financial oversight built into the architect's contract. The architect reviews the contractor's monthly pay application, evaluates whether the work billed has actually been completed and whether the amounts claimed are appropriate, and issues a certificate of payment.

Evaluate change order requests. When a change order is submitted - whether initiated by the contractor, the owner, or necessitated by field conditions - the architect evaluates whether the scope change is valid, whether the pricing is reasonable relative to the scope, and whether the change affects the design intent.

Review submittals and shop drawings. Before materials and systems are fabricated or installed, the contractor submits detailed drawings and product information for the architect's review. The architect confirms that the proposed materials and systems conform to the design specifications.

Determine the dates of substantial and final completion. The architect makes the professional determination of when the work is sufficiently complete for the owner to occupy and use the building, and when all remaining work has been completed.

These aren't theoretical responsibilities. They're contractual obligations that the architect performs as part of their professional engagement. The owner is already paying for construction oversight from a licensed professional who designed the building, understands every line on the drawings, and has a legal and ethical obligation to the owner.

What Happens When an Owner's Rep Enters This Structure

When an owner's rep is added to a project where the architect already has CA responsibilities, two overlapping oversight structures now operate on the same project - and the overlap creates real, measurable problems.

Duplicated pay application review. The architect reviews and certifies the contractor's pay application based on their site observations and their detailed understanding of the work completed relative to the contract documents. The owner's rep also reviews the pay application - questioning line items, comparing percentages complete to their own observations, potentially disagreeing with the architect's certification. The owner now has two opinions on the same document with no contractual mechanism for resolving the disagreement.

Conflicting change order evaluation. The architect evaluates a change order through the lens of design intent, scope validity, and general cost reasonableness. The owner's rep evaluates the same change order primarily through a cost lens, often without the design context that informed the architect's assessment. The architect may conclude that a $45,000 change order for a revised structural connection is fair given the engineering complexity. The owner's rep, looking at the number without the technical background, may push back on the cost. The result: delay and friction.

Filtered communication. When an owner's rep inserts themselves into the architect-owner communication flow - reviewing the architect's site observation reports before they reach the owner, adding management commentary to the architect's change order evaluations - the directness is lost. The owner receives a managed version of their architect's professional judgment instead of the judgment itself.

Authority confusion. Adding an owner's rep creates structural ambiguity. Does the owner's rep have authority to direct the contractor? Can they override the architect's CA determinations? Who resolves conflicts between the architect's assessment and the owner's rep's assessment? These questions don't have clear contractual answers because the owner's rep role isn't part of the standard AIA contract structure.

How CMAR Preserves and Strengthens the Architect's Role

Under the CMAR model, the architect retains full design authority and fulfills their CA obligations without a parallel oversight structure competing for the same territory. The CM works alongside the architect - not above them, not reviewing their work for the owner, and not filtering their communication.

The division is clean and complementary:

The architect provides design authority, construction observation, pay application certification, submittal review, change order evaluation, and the professional judgments that only a licensed architect can make. The architect's relationship with the owner remains direct.

The CM provides cost data, constructability analysis, schedule management, subcontractor procurement and coordination, quality management on the construction side, and the daily execution of building the project. The CM's expertise is complementary to the architect's - they cover different domains, and each role makes the other more effective.

During pre-construction, this collaboration is active and productive. The CM provides real-time cost feedback as design develops: "That window wall system as detailed is $280,000 installed. Here's a comparable system at $180,000 that achieves the same design intent with a different mullion profile - your call, but here's the data." The CM provides constructability review: "This connection detail at the steel-to-concrete interface will require field modification if we build it as drawn. Let's resolve it in the drawings now instead of processing a $35,000 change order during construction." The CM provides schedule input: "The structural steel fabrication lead time is 16 weeks from approved shop drawings. We need to finalize the structural design by March to maintain the August start date."

The architect focuses on design. The CM focuses on delivery. Neither is "managing" the other. The architect's creative authority is respected; the CM's construction intelligence strengthens the design by identifying cost and constructability implications early, when changes are inexpensive and collaborative rather than late, when they're disruptive and adversarial. For a deeper discussion of how the architect and CM collaborate during pre-construction and throughout the project, see our guide on the architect's role in the CMAR model.

The Architect's Experience
Architects who have worked under both models consistently report the same thing: under CMAR, they do their best work because their design authority is respected, their communication with the owner is direct, and their construction administration role is supported by a CM who provides data rather than second-guessed by an advisor who provides opinions. The question for the owner is not whether to trust their architect - they've already made that decision by hiring them. The question is whether to support that trust with a structure that reinforces the architect's role, or to undermine it with a structure that duplicates it.

The Impact on the Architect's Experience: A Comparison

Element Traditional Model (GC + Owner's Rep) CMAR Model (CM + Architect)
Design authority Architect has design authority, but owner's rep may filter or reframe design recommendations Architect has full, unfiltered design authority
Construction administration Architect certifies pay apps and reviews changes; owner's rep duplicates these reviews, creating conflict Architect certifies pay apps and reviews changes; CM provides supporting data
Communication with owner Filtered through owner's rep layer Direct - architect communicates professional judgments to the owner without intermediary
Cost feedback during design Owner's rep may provide budget opinions; contractor provides cost data only at bid CM provides construction-informed cost data in real time throughout design
Constructability review Discovered during construction (expensive) Reviewed during design in collaboration with architect (inexpensive)
Decision speed Three parties must align (architect, owner's rep, GC) Two parties coordinate (architect, CM) with owner making informed decisions
Authority clarity Ambiguous - who resolves architect vs. owner's rep disagreements? Clear - architect has design authority, CM has construction execution authority
Who the architect reports to Often the owner's rep becomes the gatekeeper The owner, directly

6. Pre-Construction - Where the Models Truly Diverge

The comparison between the owner's rep model and the CMAR model isn't just about who watches the contractor during construction. The more significant divergence happens before a single shovel hits dirt - during the pre-construction phase that determines whether the project arrives at construction with a realistic budget, a buildable design, and a clear plan, or with optimistic assumptions, unresolved coordination conflicts, and a number that's about to change.

The Advisory Model's Pre-Construction Role

Under the advisory or owner's rep model, the advisor typically engages after the owner has selected an architect and sometimes after a general contractor has already been identified or engaged. Their pre-construction contribution is evaluative: they review budgets that others have produced, attend design meetings, comment on constructability from a management perspective, and help the owner evaluate contractor proposals.

This is useful work. But it's fundamentally reactive. The advisor evaluates what others produce. They may flag that a budget "seems high" or that a timeline "seems aggressive," but they generally don't have the estimating infrastructure, trade-specific databases, or subcontractor relationships to produce independent cost analysis from the ground up.

The result is that the owner arrives at bid day - or at cost-plus estimate presentation - with a budget that's been "reviewed" but not independently developed. If the contractor's number comes in 30% over the owner's expectation, the advisor can help negotiate, but the gap already exists. The design may need to be revised. Months of design time may be lost.

The CMAR Model's Pre-Construction Role

Under the CMAR model, the CM engages during feasibility - before the architect begins design, or at minimum during early schematic design - and produces the cost and constructability analysis directly. This isn't evaluation of someone else's work. It's original analysis that the CM then stands behind with a contractual commitment.

Feasibility Report (3-4 weeks from site visit to delivery): The CM walks the site, researches the regulatory requirements, evaluates the geotechnical conditions, analyzes the permitting pathway, assesses utility access, identifies environmental considerations, develops a rough order of magnitude (ROM) cost estimate from current market data, flags long-lead procurement items, creates a preliminary risk register, and delivers a go/no-go recommendation. For a detailed look at the feasibility analysis process and what it includes, see our comprehensive guide.

Progressive Budget Development: As design progresses, the budget evolves with it - not in a vacuum, but in active dialogue between the CM and the architect. At feasibility, the ROM estimate carries a range of plus or minus 20%. By schematic design, the range narrows to plus or minus 15%. By design development, the range narrows to plus or minus 10%. At construction documents, the GMP is established - a contractual commitment with contingency defined and priced. For a detailed explanation of how the budget develops from feasibility through GMP, see our budget development guide.

Constructability Review at Each Design Milestone: At schematic design, design development, and construction documents, the CM reviews the drawings for coordination conflicts, constructability issues, cost implications, and schedule impacts. This review happens during design - when changes cost nothing but the architect's time to revise a drawing - not during construction, when every change triggers a change order.

A structural connection detail that's difficult to build as drawn costs nothing to revise at the design development stage. The same issue discovered during steel erection costs $20,000-$100,000 in field modifications, schedule delays, and change order processing. Multiply this by the dozens of coordination issues that exist in every complex set of residential construction documents, and the value of pre-construction constructability review becomes clear.

Subcontractor Pre-Qualification: Before bidding begins, the CM evaluates potential subcontractors for each trade package based on capability, financial stability, relevant experience with complex residential work, current workload, and track record on similar projects. This isn't pulling names from a directory - it's active evaluation based on the CM's working relationships and the specific requirements of the project.

The Timing Difference
The advisory model evaluates what others have produced. The CMAR model produces the analysis directly and then stands behind it with a contractual commitment. The difference isn't just scope - it's accountability. When the CM produces the cost estimate and then commits to a GMP based on that estimate, the quality of the analysis is self-enforcing. Getting it wrong costs them money. That's a different standard than reviewing someone else's number and offering an opinion.

7. Cost Transparency - What "Open Book" Actually Means

Most owners hear "open book" and assume it means they'll see invoices. On a cost-plus project, that's exactly what it means - and it's the minimum. True cost transparency is substantially more than invoice visibility, and the difference between models determines whether the owner actually understands their project's financial position or is simply receiving data they can't meaningfully interpret.

Under Cost-Plus with an Owner's Rep Reviewing Invoices

The owner or their representative sees subcontractor invoices after the work is completed and the cost is incurred. They can review whether the invoice matches the contracted scope, verify that the math is correct, and check that the work described was actually performed. This is retrospective review - the money has been spent, the work is installed, and the leverage to change the outcome is limited.

The more fundamental limitation: invoice review without procurement visibility tells you what was spent but not whether what was spent was competitive. The GC may have selected the framing sub from their regular roster without competitive bidding. The concrete price may be 15% above market because the GC has a volume relationship with a supplier that doesn't translate to the best price on your specific project. You can review every invoice with microscopic precision and still not know whether the underlying costs were competitively procured.

Under CMAR with Open-Book Accounting

The transparency under the CMAR model operates at multiple levels, each providing a different type of cost intelligence:

Bidding transparency. Every subcontractor trade package is competitively bid, and the complete bid results - every number from every bidder - are shared with the owner. On a framing package, the owner doesn't just see what the selected framing subcontractor charges. They see bids from three to five qualified framers, understand where the selected bid sits in the competitive range, and know that the procurement was market-tested.

Real-time cost tracking. The owner has access to current cost data showing committed cost versus budget for every line item in the GMP, the status and cost impact of every approved change order, contingency balance with a complete drawdown history, and projected cost at completion compared to the GMP.

Change order pricing backup. When a change order is required, the pricing includes complete backup documentation. Subcontractor quotes, material costs, labor hour estimates, equipment requirements, and the CM's markup on the change are all visible.

Contingency access controls. Every draw from contingency requires documentation of the condition that triggered the draw, the cost to address it, and the authorization to proceed. Owner-directed changes are tracked separately from construction contingency.

Final reconciliation. At project completion, the CM produces a complete cost reconciliation: the original GMP, all approved amendments, the actual cost of every trade package, all contingency usage with documentation, the final project cost, and the savings calculation. Every dollar is accounted for.

Cost Visibility Comparison

What the Owner Sees Cost-Plus + Owner's Rep Lump-Sum + Owner's Rep CMAR (Open Book)
Subcontractor bid results No - GC selects subs internally No - embedded in lump-sum Yes - all bids shared with owner
Actual cost per line item Invoices reviewed after spending Nothing - black box Real-time tracking against budget
Change order backup GC provides pricing; rep reviews GC provides pricing; rep reviews Full backup with sub quotes and material costs
Contingency status No formal contingency exists Risk premium embedded in bid (invisible) Tracked and reported with drawdown detail
When owner gets information After costs are incurred When change orders are submitted Before subcontracts are awarded and continuously during construction
What the owner can do with it Dispute after the fact Accept or reject changes Participate in procurement decisions and track costs in real time

The distinction between invoice visibility and cost transparency is not semantic. It's the difference between seeing a doctor's bill and understanding your diagnosis. One gives you numbers. The other gives you the context to evaluate whether those numbers are right.

8. Risk Allocation - Who Carries What

Risk allocation on a construction project isn't theoretical. It's intensely practical. On a complex residential project in Los Angeles - hillside site, significant foundation work, multi-agency permitting, 14-24 month construction duration - the risks that actually materialize aren't hypothetical what-ifs. They're the conditions, surprises, and complications that every experienced project manager has dealt with repeatedly.

Subcontractor Default or Poor Performance

Under lump-sum: The GC's contractual problem. The GC hired the subcontractor and is responsible for the subcontract scope within the fixed price.

Under cost-plus: The owner bears the cost. The GC will replace the subcontractor and bill the owner for all costs associated with the replacement, including the markup.

Under CMAR: The CM's responsibility within the GMP. The CM selected and contracted the subcontractor, the CM manages the subcontract, and the cost of replacement or correction is absorbed within the GMP. This is why CM firms invest heavily in subcontractor pre-qualification.

Material Price Escalation During Construction

Under lump-sum: Nominally the GC's risk - unless the contract includes an escalation clause.

Under cost-plus: The owner pays actual cost. If lumber prices increase 20% between estimate and purchase, the owner pays the 20% premium plus the contractor's percentage markup on the higher amount.

Under CMAR: The CM's risk within the GMP. If the CM underestimated escalation, the overage comes from their margin and contingency, not from the owner.

Unforeseen Site Conditions

Under all models: The owner generally bears the risk for conditions that were genuinely unforeseeable. This is true under every delivery model because no contract can allocate the risk of the truly unknown.

Under CMAR: The construction contingency within the GMP provides a first buffer. And because the CMAR model includes a thorough feasibility analysis before design begins - including geotechnical evaluation and site condition assessment - the range of "unforeseen" conditions is narrower than under models where the builder's first encounter with the site is at groundbreaking.

Design Changes After GMP

Owner-directed changes are processed as GMP amendments - documented, priced with full backup, and approved by the owner before execution. The distinction from cost-plus: on a cost-plus project, the line between "base scope" and "change" is often blurry because the scope was never precisely defined. On a CMAR project, the GMP was established against a specific set of construction documents after months of collaborative design development. Changes are identifiable, documentable, and priced independently from the base scope.

Schedule Overruns

Under cost-plus: The owner pays the extended general conditions - site supervision, temporary facilities, equipment rental, insurance, permits - for however long the project takes. Every month of delay costs the owner $40,000-$80,000+ in general conditions, plus the contractor's markup. The contractor has no financial penalty for delay.

Under CMAR: If the delay is the CM's responsibility, the CM absorbs the extended general conditions within the GMP. If the delay is owner-caused, the extended general conditions are documented and processed as a GMP amendment with full backup. The accountability is bilateral and documented. For a comprehensive overview of construction timelines and schedule management on complex Los Angeles projects, see our timeline guide.

Practitioner Takeaway
The question isn't "who do I trust?" - it's "what does the contract require?" Trust is essential in any project relationship. But on a $10M project spanning 18-24 months with hundreds of subcontractors, thousands of decisions, and millions of dollars flowing through the cost system, the contract structure determines outcomes more reliably than personal goodwill. A well-structured contract protects both parties when good intentions aren't enough. A poorly structured contract creates conflict even between well-intentioned parties.

9. When Each Model Is the Right Answer

A page that argues one model is always right isn't trustworthy. It's sales material. Every delivery model exists because it solves a real problem for a real set of conditions. The question is whether the conditions of your project match the assumptions built into the model you're considering.

When an Owner's Rep / CM as Advisor IS Appropriate

You've already selected a GC under a lump-sum or cost-plus contract. The contractual relationship exists, the incentive structure is set, and restructuring the delivery model mid-stream isn't practical. You need experienced oversight within the structure you've chosen.

Your project is relatively straightforward. Projects under $2M with standard site conditions, well-defined scope, a trusted contractor you've worked with before, and minimal anticipated changes don't generate the complexity that justifies a full CMAR engagement.

You want advisory support but prefer the GC to hold subcontracts directly. Some owners have existing relationships with general contractors they trust and simply want an independent professional reviewing costs and quality.

You're in a design competition or early feasibility stage and need process management. Before a delivery model is selected, an experienced advisor can help the owner evaluate architect proposals, manage a design competition, or navigate early decisions about project approach.

When CMAR Is the Better Structural Choice

Complex projects where budget certainty matters. Projects at $3M and above, hillside construction with significant site work, fire rebuilds in PGRAZ zones with complex regulatory requirements, substantial renovations with unknown conditions behind existing walls.

Projects requiring early feasibility analysis. When the owner needs to understand the viability of a project before committing to a full design process, the CMAR model provides construction-informed feasibility analysis that establishes realistic parameters for budget, schedule, and regulatory compliance.

Multi-agency permitting with complex regulatory pathways. Projects involving LADBS, Coastal Commission, PGRAZ compliance, HOA approvals, or other overlapping regulatory requirements need the permitting strategy integrated with the construction approach from the beginning.

Projects where the owner wants one accountable party with financial skin in the game. Under the CMAR model, the CM's margin is at risk. Overruns come from their pocket. Savings are shared. The CM's financial interest and the owner's financial interest are contractually aligned.

Projects where the architect-owner relationship should remain direct and unfiltered. If the owner values their architect's professional judgment and wants that judgment communicated directly rather than filtered through a management intermediary, the CMAR model supports that relationship. The architect's CA role is strengthened, not duplicated or undermined.

Projects where cost transparency means seeing competitive bids, not just invoices. If the owner wants to understand what the market says their project should cost - not just what their contractor says it costs - the CMAR open-book model with competitive subcontractor procurement provides market-tested pricing.

When Neither Is Needed

Small projects with a trusted contractor, well-defined scope, and a fixed budget don't require either an owner's rep or a CMAR engagement. If you're renovating a bathroom with a contractor who's done four projects for you, the oversight structure is your existing relationship. Similarly, if the owner has personal construction management experience, the advisory layer may be unnecessary regardless of the contract structure.

Decision Matrix

Project Characteristic Owner's Rep / CMa CMAR (GMP)
Project cost Under $3M, or GC already engaged $3M+ with budget certainty as priority
Scope definition Well-defined, minimal changes expected Evolving design, owner selections ongoing
Site complexity Standard conditions Hillside, poor soils, significant retaining walls
Budget certainty needed Estimate is sufficient Guaranteed maximum is required
Cost visibility desired Invoice review is sufficient Competitive bid visibility and real-time tracking
Architect's role Owner comfortable with filtered communication Owner wants direct architect relationship preserved
Pre-construction needs Evaluative review of others' work Original feasibility analysis and progressive budget development
Risk tolerance Owner accepts cost-plus risk or lump-sum change order risk Owner wants cost risk transferred to CM

10. The Reporting and Documentation Difference

The deliverables that each model produces tell you something important about the model's depth. Advisory services produce evaluative documentation - reviews of what others have generated, recommendations based on observation, and reports that synthesize the GC's information for the owner's consumption. CMAR produces the information directly, because the CM is running the project, managing the subcontractors, controlling the schedule, and tracking the costs at the source.

CMa / Owner's Rep Typical Deliverables

  • Meeting attendance notes and observation reports from site visits
  • Budget tracking based on the GC's reported costs and the advisor's independent assessment
  • Monthly status updates summarizing project progress, budget position, and open issues
  • Change order review comments with recommendations to the owner
  • Schedule review observations comparing the GC's reported progress to the published schedule
  • Communication logs documenting correspondence between parties
  • Recommendations to the owner on decisions requiring their input

These deliverables are useful. Their limitation is structural: the underlying data originates with the GC, and the advisor's reporting is only as current and accurate as the information the GC provides.

CMAR Deliverables

The CM produces the documentation directly because they're generating the data through their management of the project:

Monthly Owner Report (12-20 pages): Earned value metrics showing budget committed vs. actual expenditure for every trade package. CPM schedule updated monthly with critical path analysis. Contingency tracking with a complete drawdown log. Quality reporting, safety reporting, project photography, upcoming milestones, and risk register updates.

Weekly Progress Updates: Concise reports covering the past week's activities, the upcoming week's plan, any decisions needed from the owner, and status on open items.

Three-Week Look-Ahead Schedule (published every Monday): A rolling short-term schedule showing detailed daily activities for the next three weeks, coordinated with subcontractor commitments and material deliveries.

Real-Time Portal Access: The owner and the architect have access to a project management system containing current drawings, submittals with review status, RFIs with responses, daily field reports, and financial data including committed cost, invoiced cost, and projected cost at completion.

Change Order Log with Full Pricing Backup: Every change order logged with the originating condition, scope, subcontractor and material pricing backup, the CM's markup, GMP impact, and approval status.

Final Cost Reconciliation: A complete financial summary at project close showing the original GMP, all approved amendments, actual cost by trade, contingency usage, and savings distribution. For a complete overview of BCG's deliverable framework and reporting formats, see our deliverables guide.

Why This Matters
On a project where the CM produces the cost data, manages the schedule, and reports the results directly to the owner, the quality and accuracy of the reporting is self-enforcing. The CM can't misrepresent cost data that the owner can independently verify through the open-book system. They can't spin schedule progress because the CPM schedule is updated with actual completion dates. The documentation is a natural output of managing the project, not a separate effort layered on top of someone else's management.

11. Frequently Asked Questions

How much does an owner's rep cost for a custom home?

Owner's representative fees on custom residential projects in Los Angeles typically range from 3-5% of construction cost, though some charge hourly or on a fixed-fee basis. On an $8M project, that translates to $240,000-$400,000. This is in addition to the general contractor's markup (15-25% on cost-plus, or embedded in a lump-sum bid), meaning the total management cost to the owner includes both the contractor's compensation and the advisory fee.

What is a Guaranteed Maximum Price (GMP) and how does it work?

A Guaranteed Maximum Price is a contractual cost ceiling that the construction manager commits to in a CMAR agreement. The GMP includes all construction costs (subcontractors, materials, labor, equipment), the CM's fee, and a defined contingency for unforeseen conditions. If the actual cost exceeds the GMP, the CM absorbs the difference from their own margin. If the actual cost comes in below the GMP, the savings are shared between the owner and the CM at a pre-agreed ratio (typically 75% owner / 25% CM). The GMP is established at the completion of construction documents after a thorough pre-construction process including competitive subcontractor bidding, detailed quantity takeoffs, and collaborative design review with the architect.

Can I have both a CMAR and an owner's rep?

You can, but the question is why you'd need to. The CMAR model provides cost transparency through open-book accounting, cost discipline through the GMP commitment, and construction oversight through the CM's direct project management. The architect provides design oversight through their construction administration obligations. Adding an advisory layer on top of CMAR creates the same overlapping authority and communication friction that the model was designed to eliminate. If you don't trust your CM enough to rely on the CMAR structure, the issue isn't missing oversight - it's the wrong CM.

What happens if the project costs more than the GMP?

The CM absorbs the overage. That's the "at risk" in CM at Risk. The CM's fee, margin, and contingency are the first line of absorption. If the overage exceeds those buffers, the CM still bears the cost - this is a contractual obligation. The only exceptions are owner-directed changes (processed as GMP amendments and approved before execution) and conditions explicitly excluded from the GMP scope. The GMP is a ceiling, and the CM's financial commitment is what gives it meaning.

What happens if the project costs less than the GMP?

The savings are shared. On a GMP of $8,170,000 with an actual cost of $7,400,000, the underage is $770,000. At a 75/25 split, the owner receives $577,500 and the CM receives $192,500. Both parties benefit from the efficiency, which is why the structure incentivizes cost-conscious management. The savings distribution is calculated from the final cost reconciliation - a documented accounting with backup for every line item.

How does the CM's fee compare to a GC's markup?

A GC's cost-plus markup is typically 15-25% of construction cost, calculated as a percentage that grows as costs grow. A CM's fee in the CMAR model is typically 6-10% of construction cost, structured as a fixed amount negotiated during pre-construction. The CM's fee doesn't increase when costs increase - and since cost overruns come from the CM's margin, the CM is incentivized to control costs. On an $8M project, the gap between a 20% GC markup ($1.6M) and a 7.5% CM fee ($570K) is over $1M - before accounting for the owner's rep fee that the cost-plus structure typically requires.

Is CMAR more expensive than hiring a regular general contractor?

The CM's fee percentage is lower than a typical GC markup, and the CMAR model eliminates the need for an owner's rep fee. The total management cost under CMAR is generally 30-50% less than the combined cost of a GC markup and an owner's rep fee under the traditional model. The CMAR model also provides a cost guarantee (the GMP) that the traditional model doesn't, and shared savings that incentivize the CM to deliver the project under budget. For a detailed comparison of what construction costs in Los Angeles under different delivery models, see our cost guide.

What does "open-book accounting" mean in construction?

Open-book accounting means the owner sees every cost: every subcontractor bid, every subcontract, every invoice, every material purchase, every general conditions expense, and every contingency draw. Nothing is marked up and resold; every cost passes through at actual. The CM's fee is a separate, transparent line item - not hidden inside subcontractor markups or material cost adjustments. The owner can verify any cost at any time by reviewing the source documentation.

When should I decide between CMAR and traditional delivery?

As early as possible - ideally during project feasibility, before the architect begins design. The CMAR pre-construction process integrates with design from the beginning, providing cost and constructability data that shapes the architectural design in real time. Engaging a CMAR firm during or after construction documents means missing the highest-value phase of the model. If you've already engaged a GC, restructuring to CMAR isn't practical, and the advisory model becomes the appropriate oversight choice.

Do I need an owner's rep if I have a CMAR?

In most cases, no. The CMAR model provides cost transparency (open-book accounting), cost accountability (GMP with CM at risk for overruns), construction expertise (the CM manages the project directly), and aligned incentives (shared savings reward efficiency). The architect provides design oversight through their construction administration obligations. The conditions that make an owner's rep necessary under traditional contracts are addressed structurally by the CMAR model and the architect's existing CA role.

How does CMAR affect the architect's role?

CMAR preserves and strengthens the architect's role. The architect retains full design authority, maintains a direct relationship with the owner, and fulfills their construction administration obligations without a parallel oversight structure duplicating or overriding their professional judgments. During pre-construction, the architect gains a construction partner who provides real-time cost and constructability data that strengthens the design. For a comprehensive discussion of how the architect's role functions within the CMAR model, see our dedicated guide.

Doesn't my architect already provide construction oversight under their AIA contract?

Yes. Under the standard AIA B101 agreement, the architect has contractual obligations for construction administration including site visits, pay application review and certification, change order evaluation, submittal review, and determination of substantial and final completion. The question isn't whether to have oversight - you already do. The question is whether to duplicate that oversight with an additional layer (the owner's rep model) or support it with a construction partner whose incentives are aligned with the owner's (the CMAR model).

If my architect has construction administration responsibilities, why would I need an owner's rep?

You might need one if the contract structure with your builder creates incentive misalignment that the architect's CA role alone can't compensate for. On a cost-plus project where the contractor has no cost ceiling and no savings incentive, the architect's pay application review and change order evaluation may not be sufficient to ensure cost discipline - the architect is a design professional, not a cost auditor. Under CMAR, the cost discipline is built into the contract structure (GMP, shared savings, open-book accounting), so the architect's CA role is sufficient without an additional cost-focused oversight layer.

How do the architect and CM work together during pre-construction under CMAR?

The architect and CM work as collaborative partners throughout design, each contributing their domain expertise. The architect leads design. The CM provides cost data ("that roofing system is $45/SF installed - here's a comparable option at $32/SF"), constructability review ("this flashing detail needs modification for the hillside exposure"), and schedule input ("the custom steel fabrication is a 20-week lead item - we need to finalize the structural design by this date"). By the time the GMP is established, both professionals have collaborated through every design phase, and the GMP reflects a design optimized for both design intent and construction feasibility. For detailed examples, see our guide on the architect's role in the CMAR process.

What is the difference between CM at Risk and CM as Advisor?

CM at Risk (CMAR) and CM as Advisor (CMa) are fundamentally different accountability structures despite sharing the "construction management" label. Under CMAR, the CM holds the subcontracts, provides a Guaranteed Maximum Price, absorbs cost overruns, shares in savings, and operates with open-book accounting - the CM has financial skin in the game. Under CMa, the advisor provides recommendations, reviews costs, and reports to the owner - but doesn't hold subcontracts, doesn't commit to a cost ceiling, doesn't absorb overruns, and doesn't share in savings. For a broader comparison of all major delivery methods, see our delivery methods guide.

What types of projects are best suited for CMAR?

CMAR provides the most value on projects where complexity, cost uncertainty, or regulatory requirements make budget certainty critical: custom homes over $3M, hillside construction with significant site work, fire rebuilds in regulated zones, major renovations with unknown conditions, projects with multi-agency permitting requirements, and any project where the owner prioritizes cost transparency and aligned incentives.

How does the GMP get established?

The GMP is the product of a progressive pre-construction process, not a single-point estimate. The CM engages during early design and develops the budget progressively from a rough order of magnitude at feasibility, through increasingly detailed estimates at schematic design and design development, to a final GMP at the completion of construction documents. The GMP is built from competitive subcontractor bids on every trade package, detailed quantity takeoffs, current material pricing, defined general conditions, a construction schedule, and a risk-informed contingency.

Can the GMP change after it's set?

The GMP can be amended for owner-directed changes (scope additions, design modifications, or finish upgrades initiated by the owner) and for conditions explicitly excluded from the GMP scope. Each amendment is documented with full pricing backup and requires the owner's approval before execution. The GMP does not change for conditions that the CM should have anticipated during pre-construction or for cost increases within the defined scope - those risks are the CM's to manage.

What is shared savings and how does it work?

Shared savings is the mechanism that aligns the CM's financial interest with cost efficiency. If the actual project cost comes in below the GMP, the difference is divided between the owner and the CM at a pre-agreed ratio - commonly 75% to the owner and 25% to the CM. Every dollar the CM saves through efficient procurement, smart scheduling, proactive problem-solving, and careful cost management generates $0.25 for the CM and $0.75 for the owner. The savings distribution is calculated from the auditable final cost reconciliation.

If you're evaluating how to structure your next project - whether you're in early feasibility, approaching design, or comparing delivery approaches - we can help you determine which model fits your situation.

Tell Us About Your Project   |   How Our Engagements Work

The information on this page is provided for educational purposes and reflects the author's professional experience managing complex residential projects under multiple delivery models. Fee percentages, cost ranges, and structural descriptions represent typical conditions in the Los Angeles luxury residential market and may vary by project, market conditions, and specific contractual terms. This page does not constitute legal, financial, or professional advice. Owners should consult with their attorney and financial advisor before selecting a construction delivery method. All contractual structures described should be reviewed by legal counsel before execution.